Projects
Woodside GWF-1 Project
Westlink Projects
Piles and Subsea Installation Gear

Origin(s)
Port Kelang, Malaysia Singapore
Destination(s)
BMF, Dampier, Australia
Market
Energy & Chemicals
Sector
LNG
Year
2014
Equipment
Piles and Subsea Installation Gear
Total Weight
580 mt
Project Detail
Westlink was engaged by a customer for the transportation of subsea installation equipment and infrastructure from various locations in South East Asia to the Burrup Material Facility (BMF) in Dampier, Australia for subsea works on the Greater Western Flank Phase 1 (GWF-1) project.
Scope
Multipurpose Vessel (MPP) – transportation of piles from Port Kelang to Jurong Port, Singapore
Tug and barge – transportation of subsea installation gear from Technics yard in Singapore to Jurong Port Vessel to vessel interface – tug and barge with MPP for transfer of subsea installation gear
MPP – transport of piles and subsea gear from Jurong Port to BMF, Dampier, Australia
MPP – BMF, Dampier to Singapore for return of all subsea equipment after installation complete
Highlights
Zero LTIs
Marine Warranty Surveyor approval and compliance
Specialist lifting, lashing and stowage design and planning
Vessel to vessel transfer – lift of subsea installation gear from barge to MPP
MPP selection to meet constraints of berthing at BMF including draft, LOA and others
Quarantine management and approval of used subsea equipment
On time delivery met tight construction window