Mt. Keith De-Bottlenecking Project

Westlink Projects

Structural Steel

Origin(s)

Kwinana, Western Australia

Destination(s)

Mt. Keith Mine Site, Wiluna/Leinster, Western Australia

Market

Mining & Resources

Sector

Critical Minerals

Year

2023

Equipment

Structural Steel

Total Weight

2,500 mt

Project Detail

Westlink was responsible for the end-to-end transport of structural steel, preassemblies, and conveyor trusses for BHP Nickel West’s Mt Keith De-Bottlenecking Project from a Western Australian fabrication yard.

Scope

  • Pre-shipment inspections at fabrication yard 

  • Oversize and General Haulage of structural steel from factory to mine site 

  • Oversized Traffic Management – escorts, wardens, and overhead powerline management 

  • Construction Coordination – coordination with site team to unload trailers into laydown or direct installation.

Highlights

  • Zero LTIs 

  • Delivery of one hundred and seventy-five (175) trailer loads over six (6) months. 

  • Seamless integration of Westlink personnel within the project team 

  • No missed warden / escort dates