Fertiliser Plant Shutdown Works
Westlink Projects
Process Vessels

Origin(s)
Nansha, China Hazira, India Scanzorosciate, Italy
Destination(s)
Burrup Peninsula, Australia
Market
Other Sectors and Markets
Sector
Chemical
Year
2018
Equipment
Process Vessels
Total Weight
270 mt
Project Detail
Westlink was engaged to provide multimodal logistics solutions for several process vessels including two pressure vessels and a desalination system, all stemming from various fabrication origins from around the world. These vessels were delivered and installed as major shutdown works for a fertiliser plant located at the Burrup Peninsula in Australia.
Scope
Heavy Lift Vessels (HLVs) – Port of Origin(s) to Dampier
Roll-On-Roll-Off Vessel (RoRo) – Port of Origin to Fremantle Craneage – at various locations at ports and at delivery points at site
Heavy Haulage – Port of Discharge to Burrup Peninsula fertiliser plant
Highlights
Zero
LTIs Heavy lift and haulage for 130 metric ton (mt)
Oversize transport envelope – 20 x 9 x 6 metres
Met all tight installation windows for delivery
Heavy haulage through to congested site installation points
No disruption to fertiliser production