Projects
Christmas Creek Iron Ore Expansion Project
Westlink Projects
Structural Steel, Platework and Preassemblies


Origin(s)
Tianjin, China Ho Chi Minh, Vietnam
Destination(s)
Port Hedland, Australia
Market
Mining & Resources
Sector
Iron Ore
Year
2023
Equipment
Structural Steel, Platework and Preassemblies
Total Weight
1,500 mt
Project Detail
Westlink was engaged to provide full end-to-end logistics management of structural steel, large bin sections, modules and trusses fabricated in Tianjin, China and Ho Chi Minh, Vietnam to be used int the expansion of Fortescue’s Christmas Creek mine site in the Pilbara region of Australia.
Scope
Pre-shipment quarantine inspection of structural steel in China and Vietnam
Multipurpose Vessels (MPPs) – Tianjin and Shanghai, China to Port Hedland, Australia
Oversized haulage – vessel hook Fortescue mine site
Construction coordination – coordination with site team to unload trailers for direct install or laydown
Highlights
Zero LTIs
Steel deliveries met shutdown windows for early works
Maximised section size, preassembly and stackability to reduce logistics cost and schedule
Multiple consecutive breakbulk shipments
Laydown management with delivery coordination to site according to construction schedule