Projects
Cape Lambert A Dolphin Head Life Extension Project
Westlink Projects
187 Marine Piles


Origin(s)
Taicang, China
Destination(s)
Dampier, Australia
Market
Mining & Resources
Sector
Iron Ore
Year
2020
Equipment
187 Marine Piles
Total Weight
5,100 mt
Project Detail
Westlink was engaged to provide the marine transportation of one hundred and eighty-seven (187) piles from Taicang, China to Cape Lambert Private Wharf (Port Walcott) in Dampier, Australia. These marine piles were used in the refurbishment of Rio Tinto’s Cape Lambert A Wharf for the Dolphin Head Life Extension Project.
Scope
Pre-shipment inspections at pile fabrication yard in Taicang, China
Multipurpose Vessel (MPP) – transportation of piles from Taicang to Port Walcott
Site coordination – quarantine clearance at non-proclaimed port, coordination of delivery to laydown
Highlights
Zero LTIs
Marine Warranty Surveyor approval and compliance
Specialist lifting, lashing and stowage design and planning
MPP selection to meet constraints of berthing at Port Walcott including draft, LOA and others