Origin APLNG Project

Concrete and FBE Coated Line Pipe

Project Detail

Westlink was engaged to provide a multimodal logistics solution for 520 kilometres of large diameter concrete and FBE coated line pipe from a coating facility in Kuantan to Gladstone Port for Origin’s APLNG Project. The delivered pipe was used in for the construction of a high-pressure gas transmission line for the project to connect gas fields in the Surat and Bowen Basins to the newly constructed LNG plant on Curtis Island in Australia.

Origin(s)

Kuantan, Malaysia

Destination(s)

Origin APLNG Project Site, Gladstone, Australia

Market

Energy & Chemicals

Sector

LNG

Year

2012

Equipment

Concrete and FBE Coated Line Pipe

Total Weight

180,000 mt

Scope

  • Pre-shipment quarantine inspection at WASCO coating yard in Kuantan, Malaysia 

  • Holiday testing and cleaning of line pipe at coating yard prior to loading on vessel 

  • Multipurpose Vessel (MPP) – Kuantan, Malaysia to Gladstone, Australia 

  • Haulage – delivery and marshalling within Gladstone Port limits at laydown yard

Highlights

  • Zero LTIs 

  • 365,000 cubic metres (cbm) of pipe delivered 

  • Specialised vessel selection used for 11 consecutive monthly breakbulk shipments 

  • Large 42 inch (in) diameter pipe 

  • Zero damage to sensitive pipe coating in handling and stow