2 x Gas Compressor Packages 4 x Heat Exchanger Packages 2 x Suction Scrubber Package

Project Detail

Westlink was engaged to provide full end-to-end logistics management for the delivery of large gas infrastructure from suppliers facilities in USA and Malaysia through to greenfield project sites in rural NSW and QLD, Australia.

Origin(s)

San Diego, USA – Compressors Package Port Klang, Malaysia - Heat Exchangers Package Port Klang, Malaysia - Heat Exchangers Package

Destination(s)

NSW Greenfield sites approx. 1,200km NW Sydney QLD Greenfield sites approx. 800km W Brisbane

Market

Energy & Chemicals

Sector

Natural Gas

Year

2022 & 2023

Equipment

2 x Gas Compressor Packages 4 x Heat Exchanger Packages 2 x Suction Scrubber Package

Total Weight

750 mt

Scope

  • Heavy Haulage – Suppliers’ factories to ports of loading 

  • Ocean Freight – Heavy Lift Vessel charter, RORO shipping, and out of gauge container shipping 

  • Heavy Haulage – Port of Brisbane & Port Kembla to rural QLD & NSW sites 

  • Project Management Australian customs and quarantine clearance

Highlights

  • Zero LTIs 

  • 4,200 cubic metres (cbm) transported with heaviest lift of 55 metric ton (mt) 

  • 2 x Heavy Lift Vessel charters, with one being direct sail from Long Beach, USA to Brisbane, Australia Delivery of all cargo within specified project schedule 

  • Maximum cargo envelope – 15 x 5.1 x 3.6 metres 

  • Awarded contract for both stage 1 and stage 2 expansion projects