Kwinana Cement Plant Upgrade
MARKET MINING | SECTOR BASE MINERALS
Origin(s)
Changsu, China
Shanghai, China
Various locations in Australia
Destination(s)
Kwinana, Australia
Project
Cockburn Kwinana Cement Plant Upgrade
Equipment
Bins, Structural Steel & Trusses
Total Volume
20,000 cbm
Total Weight
5,000 mt
Heaviest Lift
100 mt
Year
2023
PROJECT OVERVIEW
Westlink managed the turnkey end-to-end logistics of stick, preassembled and modular steel fabrications and other process equipment from China and various locations around Australia to Kwinana in WA, Australia for an expansion project at Cockburn Cement’s Kwinana Cement Plant.
SCOPE
-
Pre-shipment inspections at fabrication yards in Changshu and Shanghai, China
-
Multipurpose Vessels (MPPs) – Changshu, China to Henderson, Australia
-
Oversized Haulage – Kwinana, Australia
-
Domestic Haulage – Various locations around Australian to project site
-
Containerised Logistics – Various global locations to project site
-
Construction Coordination – coordination with site team to unload trailers into laydown or direct installation
HIGHLIGHTS
-
Zero LTIs
-
20,000 cubic metres (cbm) of steel delivered with heaviest lift 100 metric tons
-
Four (4) consecutive breakbulk and heavy lift shipments
-
Transport of oversized pieces through built up urban industrial area to project site
-
Delivery to installation points and laydown at Cockburn Cement Kwinana project site