PROJECT HIGHLIGHT
ONEPACE
Rio Tinto Cape Lambert Phase 2 Project
Westlink was engaged to provide a multimodal logistics solution for structural steel sections, large bins and modules fabricated in Tianjin and Qingdao, China to be used in the construction of an iron ore screenhouse at Rio Tinto’s Cape Lambert operations in the Pilbara region of Australia.
I'm a paragraph. I'm connected to your collection through a dataset. To update me, go to the Data Manager. The Data Manager is where you store data to use in your site pages, or collect data from site visitors when they submit a form. This collection in the Data Manager is already set up with some fields and content. To customize it with your own content, you can import a CSV file or simply edit the placeholder text. You can also add more fields which you can connect to other page elements so the content displays on your published site. Remember to sync the collection so your content is live! You can add as many new collections as you need to store or collect data. With Presets, we’ve handled the page set up for you, but you can create the exact same functionality in your other site pages. To connect page elements to data, the first step is to add a dataset to the page and choose the collection you want to use. From the dataset Settings panel, you can filter or sort the available items, decide how your users can interact with the page (read/write), and more. Next, select the element you want to connect to the data, and choose the field you want to connect it to. So simple! If you want to add even more capabilities, enable Developer Tools to use JavaScript and APIs to add custom interactions and functionality to your site. To see what’s possible and get answers to your questions, check out the Wix Code Forum.
Project Numbers
Origin(s)
Tianjin and Qingdao, China
Destination(s)
Rio Tinto Cape Lambert, Australia
Project
Rio Tinto Cape Lambert Phase 2 Project
Equipment
Structural steel sections, large bins and modules for new screenhouse
PROJECT OVERVIEW
Total Volume
75,000 cbm
Total Weight
8,000 mt
Heaviest Lift
300 mt
Year
2014
SPMT and heavy haulage – fabrication yard to vessel hook at Tianjin and Qingdao
Heavy Lift Vessel (HLV) – Tianjin and Qingdao to Port Hedland and Port Walcott
Tug and barge – Port Walcott to Cape Lambert barge landing facility
SPMT – barge landing to screenhouse project site at Rio Tinto Cape Lambert operations
12K
Zero LTIs
75,000 cubic metres (cbm) transported with heaviest lift 300 metric ton (mt)
3 x full charter consecutive shipments
Maximum module envelope – 38 x 11.5 x 8 metres
HLV and tug and barge set interfacing
Zero tides missed for barge operations
Two kilometres to site via SPMT roll-off from barge with zero disruption to mining operations
Direct install from SPMT delivery point