Roy Hill WHIMS 1.5 Project

IMG_3229_edited.jpg
MARKET MINING  |  SECTOR IRON ORE
Origin(s)

Shanghai, China

Destination(s)

Dampier and Port Hedland, Australia

Project

Roy Hill WHIMS 1.5 Project

Equipment

Structural Steel, Pipe Racks, Hoppers, Tanks

Total Volume

10,000 cbm

Total Weight

1,500 mt

Heaviest Lift

45 mt

Year

2021

PROJECT OVERVIEW

Westlink managed the full turnkey logistics scope for structural steel, pipe racks, hoppers and tanks from Shanghai, China to the Roy Hill iron ore mine site in the Pilbara region of Western Australia. This steel sections and modules were used in the expansion of Roy Hill’s Wet High Intensity Magnetic Separator (WHIMS) plant.

SCOPE

  • Pre-shipment quarantine inspection of structural steel in China

  • Ocean Freight – Shanghai, China to Dampier and Port Hedland, Australia

  • Oversized haulage – from vessel hook to Roy Hill mine site

  • Construction coordination – coordination with site team to unload trailers for direct install or laydown

HIGHLIGHTS

  • Zero LTIs

  • Specialist lifting, lashing and stowage design, and planning

  • 10,000 cubic metres (cbm) of fabricated steel

  • Multiple consecutive breakbulk shipments