Offshore LNG Development

4 x Suction Piles

Project Detail

Westlink managed the full end-to-end logistics management for the transportation and delivery of steel suction piles from Kabil, Batam, Indonesia to Dampier, Australia. These suction piles were used in subsea installation for an offshore LNG development.

Origin(s)

Kabil, Batam, Indonesia

Destination(s)

Dampier, Australia

Market

Energy & Chemicals

Sector

LNG

Year

2020

Equipment

4 x Suction Piles

Total Weight

320 mt

Scope

  • Pre-shipment quarantine inspection at pile fabrication yard in Kabil, Batam, Indonesia 

  • Multipurpose Vessel (MPP) – Kabil, Indonesia to Dampier, Australia

Highlights

  • Zero LTIs 

  • Marine Warranty Surveyor approval and compliance 

  • Specialist lifting, lashing and stowage design and planning 

  • Large four (4) metre diameter piles